Hamilton MRF Container Line Upgrade

Projects Description

This project supports the installation of a second optical sorter on Hamilton’s container line and re-purposing of their existing optical to improve the capture of high value commodities and reduce process loss.  A 2014 MRF efficiency audit (CIF #816.3) recommended the installation to help increase revenue generating potential and reduce residue management costs. The proposed upgrades are expected to achieve a 4.8-year payback.

Documents Final Report: Material Recovery Facility Assessment: Implementation of Recommendations for a Second Optical and Residue Quality Control Station
Blog Post
Related Projects
Categories Best Practices | MRF | Operations | Processing |

 


 

More Information
Project # 849
Proponent Hamilton, City of
CIF Funding $705,000
Date Approved September 29, 2014
Date Completed March 4, 2018