This application involves the installation of a portable conveyor and overhead magnetic separator to allow Strong Township to separate their ferrous and aluminum streams and secure improved market pricing. The project also includes expansion of the current Coverall style building to aid traffic flow of residents and operations and supporting funding to improve signage and customer P&E. The CIF has provided $22,950 or 46% of the funds required to complete this project. A payback of six years is expected.

Documents Final Report: Recycling Innovations: Transfer Station Upgrade
Blog Post
Related Projects Project #354
Categories Best Practices | MRF | Operations |

 


 

More Information
Project # 581.11
Proponent Strong, Township of
CIF Funding $22,950
Date Approved August 9, 2010
Date Completed September 16, 2011