Installation of Compactor Systems

Projects Description

This project involves the installation of compaction systems for fibres and containers at four of Sequin Township’s busiest depots to reduce hauling costs. The system is expected to cost approximately $450,000 and achieve a project payback of approximately 4 years. The CIF will contribute approx $210,000 or 47% funding.

Documents Final Report: Installation of Compactor Systems
Blog Post
Related Projects
Categories Best Practices | Compactors |

 


 

More Information
Project # 832.3
Proponent Seguin, Township of
CIF Funding 4210,600
Date Approved October 1, 2013
Date Completed June 7, 2015